LACDMH staff are readily available to the agencies throughout the process to discuss concerns and answer specific questions about their proposed project proposal. In general, the agencies that take greatest advantage of their assistance and guidance are able to move their proposals forward quickest.
Roughly, you should plan for 8-13 weeks to be approved and sign your TNFA, so you may begin the project work you include for reimbursement:
- 4-6 weeks for Level 1
- 2-3 weeks for Level 2 , i.e. MHSA application approval
- 2-4 weeks for TNFA (legal agreement) execution (sometimes less)
- project work can commence
- 2 weeks to receive 20% start-up funds, if you requested this; 4 weeks from the date DMH receives a properly completed Start-Up invoice;